The following infrastructure improvements are scheduled to take place next week:
📍 S. Washington / City Hall Parking Lot
-Concrete crews will complete the sidewalk installation at the City Hall entrance.
-Preparation work for paving will continue.
-Topsoil will be placed, and green spaces will be seeded.
📍 SE 4th Street
-Pavement crews will begin milling and rebuilding the roadway.
-This work is expected to take most of the week.
-Access to Fortunata's Bakery will remain open.
📍 Kent Place
-The contractor will be installing approximately 200 linear feet of sewer line.
-This work is anticipated to continue throughout the week.
We appreciate your patience and cooperation as these important improvements are completed.