The water main construction on NE Front St. and Rehoboth Blvd. is nearing completion. Underground piping is complete and rehab construction has begun. We will publish a weekly update through project completion.
Wednesday, June 1 Update: The contractor completed saw cutting and final paving preparations last week. Paving will begin today. All work will be completed during the daytime and will use lane shifts and intermittent lane closures.
Overall project note: Once the water main construction is complete, the construction area from Rehoboth Blvd. to 4th St. will be milled and paved, while NE Front St. from 4th St. to Washington St. will be milled in preparation for the DelDOT Streetscape Project. This project will transform the entire look of that gateway into the City complete with brick sidewalks, crosswalks, sidewalks on both sides of the street and a protected bike lane.